Lagos Ibadan Expressway To Be Delivered 12 Months Ahead Of Schedule

Lagos Ibadan Express Way
FOR motorists and commuters eagerly awaiting the completion of the reconstruction work going on at the Lagos-Ibadan Expressway, relief would come earlier than anticipated as the Minister of Works, Mike Onolememen at the weekend declared that the project could be delivered 12 months earlier than the initial 48 months schedule. 
  Speaking during an interactive forum with editors in his office in Abuja, Onolememen assured that with the pace of work and the mode of funding of the project, the contractors handling the project, Julius Berger Nigeria Limited and the Reynolds Construction Company (RCC), could deliver the road in 36 months, one year earlier than the schedule period for its completion.
   He said the construction project, which would gulp a total of N167 billion is been executed using a financial architecture that commits the Federal Government to providing N50 billion within two years, while the balance of N117 billion is being sourced from the private sector.
  “What we did was that the Federal Government will contribute about N50 billion into the common purse, and from the 2014 budget alone, we are contributing N25 billion and the final N25billion, which will now form the total of the Federal Government commitment to the project will be part of the 2015 budget. But beyond that, the outstanding money which totals almost about N120 billion is being raised through a private finance initiative and that was how the project was approved, and that is how we are actually realizing it.
  According to the Minister, the private finance initiative, which is driving the project, involves the Infrastructure Bank as fund arranger, the Nigeria Sovereign Investment Authority, as well as a number of banks and financial institutions. As a result of this funding arrangement, the road will be tolled to enable investors recoup their investments and also maintain the road.
  “When you borrow money from the private sector to do an infrastructure project, the project itself should pay back for that infrastructure. It is one of the things we need to do to guarantee the sustenance of our private highways across the country.
 “The Lagos Ibadan Expressway is a major economic arterial route. For government, doing that road is not just a social service; it is also an economic service. And because it is an economic route, it can benefit from private sector investments and such investments can be recouped even from the critical infrastructure itself,” he said.
   Onolememen noted that the pace of work has been very impressive, adding that the contractors are moving faster than expected, just as he expressed optimism that the two sections would be completed before the 48-month period.
    On the perennial disagreement between states and the Federal Government over the repairs and refunds of Federal roads within states, the Minister revealed that the Federal Government would soon offload Federal roads that are within five kilometers of cities to states. The policy is informing the construction of by-passes to remove the Federal Government from the responsibilities of internal roads in the state capitals.
“When we had the Council of Works meeting in Lagos in 2012, one of our resolutions at that meeting was that we are to create a-5Km radius around states capital or cities where Federal roads traverse. Federal roads basically ought to connect one state to another.
We are now experimenting with the creation of by passes, so that, we are not brought into the issue of urban alignment because it is not the Federal Government’s responsibility to provide urban alignments and accesses to residences, offices and businesses.
  “The Federal Government doesn’t collect taxes from those people. It is the state government that collects those taxes, and they should be able to fix those roads.

9jawedey

9jawedey

No comments:

Post a Comment

Have your say, post your comments»»»

For more updates»»»Mail us: 9jawedey@gmail.com

You can also read.....

7 Signs Your Man Truly Loves you

How Many Nigerian Workers Have Other Sources of Income?

How Many Nigerian Workers Have Other Sources of Income?
One Extra Naira Note

8 Things Women REALLY Don't Like In Bed

Send Mail

We would like to hear from you:Send Mail to 9jawedey

Like our page for more updates....https://www.facebook.com/9jawedey

Get the Best Breaking News and Entertainment Gist on BBM, Add 7AA4BC08






9jawedey


Agat Energy

Agat Energy
Agat Fresh Air is designed to effectively create conducive atmosphere for inhaling and exhaling. It works on removing offensive odor and stale atmosphere. It is designed with a combination of fragrances that gives the atmosphere a friendly smell. Be a distributor of Agat fresh air today or get one for yourself. Call: +2348182004800; 08123245200; BB-PIN: 24D44407

Place your advert

9jawedey Archive